- The compromised state of the timber towers and superstructure of the original Dry River Suspension Bridge resulted in closure in 2007.
- JBI Helicopter Services performed delivery and removal of bridge material from a staging area near Highway 302. All helicopter operations were completed in one day.
- Seattle Bridge staged 21 lifts for delivery to the bridge site, with the bridge demolished and staged for removal on the outbound leg.
- Ken Gilman installs a new lattice column tower, with mainlines draped across the river.
- Lattice column tower, interior.
- Dry River original mainlines draped in new saddles.
- Dry River Mainlines girthed to relieve and replace saddles.
- Martin Walz installing floorbeam assemblies from the skyline.
- New weathering steel floorbeams and suspender assemblies hung from original mainlines.
- Stringer installation underway; note the welded steel angle outboard of the stringers for installation of timber posts.
- Ken Gilman and Austin Thompson completing superstructure installation.
- Bridge installation nearly complete; tImber rails and posts recreate appearance of the original timber structure.
- Dry River Suspension Bridge, Winter 2009.
- Dry River Suspension Bridge, Fall 2009.